In contracting, the period after award when parties fulfill obligations is called which phase?

Master accounting terms with our ACFE practice test. Study with flashcards and multiple choice questions, each question has hints and explanations. Prepare for your exam today!

Multiple Choice

In contracting, the period after award when parties fulfill obligations is called which phase?

Explanation:
After a contract is awarded, the work moves into the post-award/administration phase. This is the period where the parties carry out and verify performance, administer the contract terms, process payments, manage changes, monitor compliance, and address issues until the contract is completed and closed. It’s specifically about executing and administering the agreement rather than planning or signing it. The other options don’t fit because they refer to unrelated concepts: a penetration test is cybersecurity testing, the going concern principle is an accounting assumption about ongoing operations, and a contract is the document itself, not the phase of performance.

After a contract is awarded, the work moves into the post-award/administration phase. This is the period where the parties carry out and verify performance, administer the contract terms, process payments, manage changes, monitor compliance, and address issues until the contract is completed and closed. It’s specifically about executing and administering the agreement rather than planning or signing it. The other options don’t fit because they refer to unrelated concepts: a penetration test is cybersecurity testing, the going concern principle is an accounting assumption about ongoing operations, and a contract is the document itself, not the phase of performance.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy